Drywall
Room in, buy list out — sheets with waste, and the screws, mud and tape that never make it onto the list.
Your buy list
0
sheets of 4 × 8- Wall area
- —
- Ceiling area
- —
- Ceiling sheets
- —
- Screws
- —
- Joint compound
- —
- Tape
- —
- Corner bead
- —
- Estimated cost
- —
Openings deducted; waste added after.
Counting sheets
Wall area is the perimeter times the ceiling height — twice the length plus twice the width, multiplied by how tall the room is. A standard door takes 21 square feet off that and a window about 15; change either size if yours differ. If the ceiling is going on too, add the floor area again. Already have the square footage? Switch the form to square feet and enter the walls directly, with the ceiling in the extra box. Divide the total by the sheet size, add waste, and round up: sheets are not sold in halves.
Ceilings are often hung in a different board than the walls, 5/8 inch or sag-resistant 1/2 inch, and commonly in 4 × 12 sheets. Choose a ceiling sheet size and the walls and the ceiling are counted separately: waste is added to each, and each is rounded up to whole sheets on its own, so the list shows both sizes. Screws, compound and tape stay on the combined area. The count is by size only; thickness changes the price and the weight, not the number of sheets.
Waste on drywall is not the same waste as on flooring. Most of it is offcuts you cannot reuse — the strip above a door, the corner that broke carrying it upstairs, the sheet measured against the wrong stud. Ten percent covers a square room. Add more for a room full of angles, soffits or a stairwell.
The materials nobody lists
Hanging is a day; finishing is three. Every 4 × 8 sheet takes about 32 screws at 12 inches on centre, and longer sheets take more in proportion — call it a pound of screws for every nine sheets of 4 × 8. A 4.5 gallon box of all-purpose compound covers roughly 475 square feet of board through tape and two coats, and paper tape runs about 37 feet per 100 square feet. Buy all of it at once; running out of mud on a Sunday afternoon costs more than the box did.
Then it gets painted
New board drinks paint. Prime it with a dedicated drywall primer — the paper and the dried compound absorb at completely different rates, and colour over unprimed board flashes at every joint. Take the same room dimensions to the paint calculator for the gallons, and count the primer as a separate coat.
On the counter
The assumptions and limits this calculator uses. The form exposes the settings you can change; fixed allowances are described below.
- Sheet size
- 4 × 8 = 32 sq ft by default; 4 × 10 and 4 × 12 in the dropdown
- Ceiling sheet
- Same as the walls by default, counted together. Pick a different size and walls and ceiling are counted separately, waste on each, each rounded up on its own. Only in length × width mode; in square feet the ceiling rides in the wall area and the wall size applies. Thickness (5/8 in, sag-resistant 1/2 in) is not part of the count
- Waste
- 10 % — cut-offs, damaged corners and the piece that measures wrong
- Openings
- Each door deducts 21 sq ft and each window 15 sq ft; both sizes are adjustable
- Screws
- About one per square foot of board at 12 in on centre (32 on a 4 × 8, 48 on a 4 × 12); about 300 #6 screws to the pound
- Compound and tape
- One 4.5 gal box per 475 sq ft; 37 ft of tape per 100 sq ft, on the combined wall and ceiling area even when the ceiling sheet is different
- Corner bead
- One floor-to-ceiling run per outside corner, in whole 8 ft or 10 ft sticks; offcuts are not spliced
- Estimated cost
- Before tax, and only the sheets — screws, compound, tape and bead are not priced. Ceiling sheets in a different size are priced only if you enter a ceiling sheet price
Questions from the aisle
How many sheets of drywall for a 12x12 room?
Walls are 384 square feet gross, 333 after a 21 square foot door and two 15 square foot windows come off; add a 144 square foot ceiling and it is 477. At 10% waste on 4×8 sheets that is 17 sheets for walls and ceiling — plus two pounds of screws, two boxes of compound and 200 feet of tape. Walls only, it is 12 sheets.
4x8, 4x10 or 4x12 sheets?
Longer sheets mean fewer butt joints, which are the hardest joints to hide. On an 8 foot wall, 4×12 sheets hung horizontally can span a whole wall with one seam at 4 feet. They are also heavy and awkward — 4×8 is what fits in most vehicles and up most staircases.
Can the ceiling be a different sheet from the walls?
Yes. Ceilings are often hung in a different board than the walls, such as 5/8 inch or sag-resistant 1/2 inch, and commonly 4×12 so there are fewer joints overhead. Pick a ceiling sheet size and the walls and ceiling are counted separately, each with its own waste and rounded up on its own. In the 12×12 room with 4×8 walls and a 4×12 ceiling: 333 sq ft of wall at 10% waste is 12 sheets of 4×8, and 144 sq ft of ceiling at 10% waste is 4 sheets of 4×12, 16 sheets against 17 of 4×8 for everything. Screws, compound and tape stay on the combined area: 2 pounds, 2 boxes and 200 feet. The calculator counts by size, not thickness. Thickness changes the price and the weight, so enter the price of the sheet you are buying.
How much joint compound do I need?
About one 4.5 gallon box per 475 square feet of board for a taped, three-coat finish. Skim-coating for a level 5 finish roughly doubles it, and hot mud used for the first coat comes in bags you mix yourself.
How much corner bead do I need?
One run, floor to ceiling, for every outside corner — the ones that point into the room, like the end of a wing wall or a boxed-in chimney. Enter the count and the calculator multiplies by the ceiling height and rounds up to whole sticks: two outside corners in an 8 foot room is 16 feet, two 8 foot sticks. On a 9 foot wall each corner needs a 10 foot stick, or two 8 foot ones. Inside corners take paper tape, which is already in the tape line.
Do I deduct doors and windows?
Deduct the openings, but do not deduct the waste. The board cut out over a door usually cannot be used anywhere else, so this calculator subtracts openings from the area and then adds the waste percentage back on top.
The reasoning behind this one
Drywall: sheets, seams, mud and tape
Where the assumptions above come from, what changes them, and the mistakes that cost a second trip. Free to read, no account needed.