Concrete: bags or a ready-mix truck.

Cubic yards, bag counts, and the size of pour where mixing by hand stops making sense.


Concrete is the one material on a DIY list where the quantity decides the method as well as the price. A dozen bags is an afternoon with a wheelbarrow. Sixty bags is two and a half tons of material, mixed and placed by hand, and the first batch is setting before the last one is mixed. The arithmetic is simple. Knowing which side of that line your pour lands on is the useful part.

Volume first

Every concrete estimate starts as a volume, and the only unit trap is thickness, which is measured in inches while everything else is in feet.

Cubic feet = length ft × width ft × (thickness in ÷ 12)

Cubic yards = cubic feet ÷ 27

Then add a waste allowance. Ten percent is the usual figure, and it is not really waste. Subgrade is never perfectly flat, forms bow slightly, excavations come out a little deep, and some concrete stays in the mixer and the wheelbarrow. Running short in the middle of a pour leaves a cold joint, a weak seam where fresh concrete meets concrete that has already started to set. A spare bag costs a few dollars. A cold joint in a slab is permanent.

Worked example: a 10 × 10 ft pad, 4 inches thick.

  1. 10 × 10 × (4 ÷ 12) = 33.3 cubic feet
  2. Add 10%: 36.7 cubic feet
  3. ÷ 27 = 1.36 cubic yards
A 10 by 10 foot, 4 inch slab with 10 percent waste is 1.36 cubic yards: 62 eighty-pound bags weighing 4,960 pounds, or 82 sixty-pound bags, against a single 1.5 yard ready-mix order.
The same 1.36 cubic yards as bags and as a truck order. Each square on the left is one bag you lift at least twice.

Turning volume into bags

Bagged concrete is sold by weight and yields by volume. The yields printed on the bags are close to these:

Bag Yield
40 lb 0.30 cu ft
50 lb 0.375 cu ft
60 lb 0.45 cu ft
80 lb 0.60 cu ft

Divide the cubic feet by the yield and round up. The example pad is 36.7 ÷ 0.6 = 62 bags of 80 lb, or 36.7 ÷ 0.45 = 82 bags of 60 lb. The concrete calculator does this for each bag size and shows the cubic feet beside the count, so you can check it against the label on the pallet you are buying from.

The 80 lb bag is cheaper per cubic foot and means fewer bags to open. The 60 lb bag is easier to lift and pour cleanly into a mixer. Pick on your back, not on the price difference.

Where the line is

The calculator flags ready-mix once a pour reaches one cubic yard. That is a planning threshold, not a rule, and it moves with your crew and your mixer. The things that set it:

A short-load ready-mix order usually carries a minimum charge or a short-load fee, so a truck for half a yard is poor value. Somewhere between one and two yards, most people find the truck cheaper once they count a mixer rental, two trips with a trailer, and a second pair of hands for the whole day.

Ready-mix is ordered in fractions of a yard; many suppliers take quarter-yard steps, some only half yards. Round your total up to their step, not down. The example pad is a 1.5 yard order.

Footings and post holes

Round pours use the area of a circle instead of a rectangle:

Cubic feet per hole = π × (diameter in ÷ 24)² × depth ft

Six deck footings, 10 inches across and 3 feet deep, come to 10.8 cubic feet with 10% added, which is 18 bags of 80 lb. Set a 4×4 post in each hole first and the post displaces about 1.7 cubic feet across the six holes, allowance included, which brings it to 16 bags. The calculator subtracts the post when you tell it there is one.

Holes are where hand-mixing makes the most sense. Each one is a separate small pour, there is no surface to finish, and a cold joint between two holes does not exist.

Things the volume does not include

A short checklist

  1. Measure length, width and the real thickness, including any thickened edge.
  2. Work out cubic feet, add 10%, convert to cubic yards.
  3. Under about a yard: count bags, and plan the mixing so placement is continuous.
  4. Over a yard: call two ready-mix suppliers, ask their minimum, their step size and their short-load fee, and book the pour for a cool morning.
  5. Have the base compacted, the forms braced and the finishing tools out before the first bag is opened or the truck arrives.

The calculator’s figures are planning estimates from geometry and published bag yields. They do not replace a design for a structural slab or a footing that carries a building load; that is a question for your local building department.